BuildSuite Core

BuildSuite Core

Open in ChatGPT
Ask ChatGPT about this page
Open in Claude
Ask Claude about this page

Bill of Quantities (BOQ)

The BOQ lists the work for a job with quantities and rates, and gives the estimated cost. It is the base for tendering, budgeting and cost tracking.

BOQ list view

Create a BOQ

Click + New BOQ and choose what it is for:

Option Use it when
New enquiry There is no project yet. Link the BOQ to a project if you win the job.
Existing project You need a new version of that project’s BOQ

Enter a Title, pick a Customer if you want one, and click Create draft. Then add groups and items, import an estimate template with Import Template..., or import from Excel.

BOQ Creation

BOQ Structure

Level What it is Example
Group A section of work. The code is generated automatically (A, B, C…) if left blank. A — Civil Works RCC
Item A measurable piece of work, often from an assembly A.06 RCC for decking slab, 38 m³
Sub-item The rate breakdown of an item, from the Rate Master Cement, steel, mason, mixer

11.4.3 BOQ fields

Field Type Mandatory Notes
Title Data Yes Identifies the estimate until it has a project
Customer Link: Customer No Who the job is priced for
Project Link: Project No Empty for an enquiry. Set when the job is won.
Revision — Auto R1, R2…
Status — Auto Draft / Submitted / Approved / Replaced
Tax Rate Percent No Default 18%
Margin Rate Percent No Default 10%
Description Text No

11.4.4 Item fields

Field Notes
Code and Description e.g. A.06 RCC for decking slab
Unit, Plan Qty, Rate Planned amount = Plan Qty × Rate
Quantity Source Manual / Assembly / Template / Takeoff
Assembly The assembly the item came from, if any
Work Package (WP) The work package the cost belongs to
Task Optional. Used to calculate actuals.
Cost Head Material / Labour / Equipment / Subcontract / Preliminaries / Other
Fulfilment Procure / Manufacture (make-or-buy)

BOQ Detailed view

11.4.5 Calculations

  • Item amount = Quantity × Rate
  • Sub-item quantity = Coefficient × Item quantity
  • Group total = Sum of its items
  • BOQ total = Subtotal + Margin + Tax

Amounts are recalculated whenever a quantity or rate changes.

11.4.6 Approval and revisions

A draft is sent with Submit for approval. Each BOQ record is one revision. A project can have only one Approved revision, and approving a new one changes the previous one to Replaced. An approved BOQ is read-only. To change it, use + Revision, which creates a new draft. A revision can also come from an approved scope change order (see 10.3). In that case the page shows “from SCO …”.

11.4.7 Planned, committed and actual

For each line and group the BOQ shows:

Column Meaning
Planned Plan Qty × Rate
Committed Value of submitted purchase orders and subcontract work orders against the line’s cost code
Actual Cost booked so far. Refresh it with Recalc actuals.
Variance Actual against Planned, in %

Material ordered on the project without a cost code is not counted as committed. A banner shows its value with a link to the purchase orders.

11.4.8 Page actions

Action What it does
Submit for approval Sends a draft for approval
Recalc actuals Recalculates actuals from the linked tasks’ progress
+ Revision Creates a new draft revision from this BOQ
Compare to R… Shows the changes against the previous revision
Import Template... Adds the groups and items of an estimate template
Import from Excel... Imports lines from an Excel or CSV file. The system matches the columns and asks you to approve any units it doesn’t recognise.
Export CSV Downloads the BOQ lines
Clone... Copies the BOQ
Set up work packages and tasks... Creates the project’s work packages and tasks from the BOQ
Delete Deletes the BOQ (drafts only)

BOQ list: The list shows each BOQ’s ID, what it is for (a project, or “Estimate · not yet won”), revision, status, planned, actual and variance. The cards at the top count Approved, Draft and Submitted BOQs and show the total planned value of approved BOQs.

Last updated 1 day ago
Was this helpful?
Thanks!