**Field Attendance** is the daily attendance sheet for one project. The list shows each sheet’s **ID**, **Project**, **Date**, number of **Employees** and **Status**. In a single sheet you record which workers came, which were absent or on half day, any overtime, and which cost code their work belongs to. When the sheet is submitted, BuildSuite posts the attendance, works out the labour cost and charges it to the project’s estimate.

**Open it from:** Sidebar → **Workforce** → **Field Attendance**



![](/files/image83a45d.webp)
*Field Attendance list*



**Before you begin**

- The workers must exist as **Field Employees** and should be allocated to the project.
- For labour cost to reach the estimate, the project’s BOQ must have cost codes.
- You need a role with permission to create and submit attendance. See **Roles and permissions**.



### Create a Field Attendance sheet

1. Open **Field Attendance** and click **+ Add Field Attendance**.
2. Select the **Project** and the **Date**.
3. Add the workers. You can bring in every worker allocated to the project in one click, or add them one by one.
4. For each worker, set the **Status**, any **OT Hrs** and the **Cost Code**, and add a comment if needed (for example “Left early”).
5. Save the sheet. It is saved as **Draft**.
6. Check the sheet and click **Submit**.



![](/files/imagefc4097.webp)
*Field Attendance Creation*

### The attendance sheet

#### Summary cards


| Card            | What it shows                                                              |
| --------------- | -------------------------------------------------------------------------- |
| **Project**     | The project the sheet is for                                               |
| **Cost Code**   | The cost code of the work done. Shows **Not coded** if no cost code is set |
| **Present**     | Workers present out of workers on the sheet, for example 4 / 5             |
| **Labour Cost** | The wages for this sheet, including overtime                               |


#### Employee list


| Column                   | What it means                                        |
| ------------------------ | ---------------------------------------------------- |
| **Employee**, **Emp ID** | The worker                                           |
| **Status**               | **Present**, **Half Day** or **Absent**              |
| **OT Hrs**               | Overtime hours worked that day                       |
| **Cost Code**            | The BOQ cost code the worker’s labour is charged to  |
| **Comments**             | A note on the worker’s day, for example “Left early” |


### Status and actions


| Status        | What it means                                                            | Actions                          |
| ------------- | ------------------------------------------------------------------------ | -------------------------------- |
| **Draft**     | Saved, not yet posted                                                    | **Edit**, **Submit**, **Delete** |
| **Submitted** | Attendance and labour cost are posted. The sheet can no longer be edited | **Cancel**                       |
| **Cancelled** | The posting is reversed                                                  | Amend to correct it              |


### What happens when you submit

- The **Labour Attendance** and **Overtime Attendance** registers are created from the sheet.
- The labour cost of each row is posted to the estimate’s **Actual** under that row’s cost code.
- Rows with **no cost code** are still recorded in attendance, but their cost does **not** reach the BOQ Actual. Before you submit, the sheet warns you how many rows have no cost code.

> **Tip:** Always set a cost code before submitting. Otherwise the project’s actual labour cost will be understated.

### Correcting a sheet

The Labour and Overtime Attendance records come from the sheet and can’t be edited on their own. To correct a submitted sheet, **Cancel** it, amend it and submit it again.





![](/files/imagef5939b.webp)
*Field Attendance Detailed View*