title: "Procurement workspace"
space: "BuildSuite Core"
url: "https://wiki.buildsuite.io/core/work-package-management/procurement-workspace"
updated: "2026-11-16"
---

The **Procurement** workspace manages buying materials and services for projects, from the site’s request to the supplier’s bill:



**Material Request → Purchase Order → Purchase Receipt → Material Consumption → Supplier Bill**



The site raises a **Material Request**. Once approved, it’s ordered from a supplier with a **Purchase Order**. Goods arriving at site are recorded in a **Purchase Receipt**, which puts them into the project’s store. Material used on the project is issued out with **Material Consumption**. The supplier’s invoice is entered as a **Supplier Bill**. Each line can carry a **cost code**, so its cost lands on the right part of the project estimate.

These are standard ERPNext documents: Material Request, Purchase Order, Purchase Receipt, Stock Entry and Purchase Invoice. BuildSuite adds the project, cost code, approval and estimate checks, and puts them on one screen.



`Open it from: Sidebar → Procurement`



![](/files/image1af21c.webp)


| Link                      | What it opens                                                             |
| ------------------------- | ------------------------------------------------------------------------- |
| **Procurement Dashboard** | A live summary of open requests, orders, site receipts and rate variances |
| **Material Requests**     | Materials the site has asked for                                          |
| **Purchase Orders**       | Orders placed with suppliers                                              |
| **Purchase Receipts**     | Goods received at site                                                    |
| **Supplier Bills**        | Supplier invoices (this opens **Project Finance → Bills**)                |
| **Material Consumption**  | Material issued out of site stock                                         |
| **Suppliers**             | The supplier master (this opens **Project Finance → Suppliers**)          |
| **Items**                 | The item master                                                           |




**Reports**


| Report                             | What it shows                                                   |
| ---------------------------------- | --------------------------------------------------------------- |
| **Requests waiting to be ordered** | What the site has asked for that isn’t on an order yet          |
| **Delivery follow-up**             | Open orders by the date they were needed, and which are late    |
| **Material at site**               | Received minus consumed, for each item at each project store    |
| **Purchase rate vs estimate**      | What you’re paying against the QS rate in the Rate Master       |
| **Purchase register**              | Every order line, with supplier, item, quantity and rate        |
| **Consumption by cost code**       | Material issued to site, against the cost code it was booked to |


> **Note:** You see only the links, reports and figures your role has permission for. See **Roles and permissions**.

### Procurement Dashboard

**Summary cards**

- **Open Material Requests**: the number and value of requests not yet fully ordered.
- **On Order · Awaiting Delivery**: purchase orders not yet fully received, with their value.
- **Received This Week**: purchase receipts in the last 7 days.
- **Above Estimated Rate**: PO lines priced above the Rate Master.



![](/files/image3905c0.webp)

**Needs action** lists approved requests waiting to be ordered (with how long the oldest has waited), overdue deliveries, partial deliveries (orders 1–99% received) and goods received but not billed. Click a row to open that list.

**Recent site receipts** shows the latest receipts with item, quantity, project, supplier, date and receipt ID. Click **View all** to open Purchase Receipts.