A **Subcontractor Bill** records what the company owes a subcontractor for work done. On a work order, it bills the **certified quantity measured since the last bill**, holds back retention, applies tax, TDS and any discount, and works out the net amount payable. When the bill is submitted, 



`Open it from: Subcontract → Subcontractor Bills`



**Before you begin**

- For a bill on a work order, the work order must be **submitted** and have at least one **certified** Measurement Book.
- The tax templates and expense account should be set up in accounting.

### Two kinds of bill

**From Work Order** is the normal running bill. You pick the work order, and the lines are filled in from its schedule of values and certified measurements. You can also start one with **+ Bill progress** on a work order, or **+ Subcontractor bill** on a certified Measurement Book.

**Direct (no work order)** is for one-off or lump-sum charges that aren’t part of a work order. You select the subcontractor and project and type the charge lines yourself.

### Create a bill from a work order

1. Open **Subcontractor Bills**, click **+ New** and keep **From Work Order** selected.
2. Pick the **Work order**. The subcontractor and project are filled in from it.
3. Set the **Date**. If you have the subcontractor’s invoice, enter its number and date.
4. Check the lines under **This period**. They are worked out from the certified Measurement Books and can’t be typed in.
5. Click **Create subcontractor bill**. It is saved as **Draft**.
6. On the bill page, add taxes, TDS, a discount or an advance if needed. Then **Submit**.

![](/files/image26d431.webp)

### Create a direct bill

1. Open **Subcontractor Bills**, click **+ New** and choose **Direct (no work order)**.
2. Select the **Subcontractor** and **Project**. The project sets the accounting company.
3. Set the **Date**, and the subcontractor’s invoice number and date if you have them.
4. Under **Charge lines**, click **+ Add line** for each charge, with what is being billed, the amount and, if known, a cost code.
5. Click **Create subcontractor bill**. Taxes are added on the bill page.

![](/files/image1a81b6.webp)

### How the quantity is worked out

On a bill from a work order, each line bills only what hasn’t been billed before:

> **This period qty** = Measured to date (from certified Measurement Books) − Previously billed qty
>
> **This period amount** = This period qty × Rate

The quantities are fixed when the bill is raised. Work certified later goes on the next bill.

> *Example:* 2,400 m² of tile laying is certified and none has been billed, so this period qty is 2,400 m². At ₹85/m² the gross bill value is **₹2,04,000**.

### The bill page

The top shows the bill’s status and payment status, the subcontractor and project, and five cards: the **Work Order** and its delivery type (or the **Subcontractor**, on a direct bill), **Date**, **Gross this period**, **Retention** with its % and **Net payable**. After submitting, the bill also shows its linked **Purchase Invoice** and the **Outstanding** amount.

<picture>
  <img src="/files/imageceb7ed.webp" alt="" width="704">
</picture>

The page has these sections:

- **Subcontractor Invoice reference** (optional): the subcontractor’s own invoice number and date.
- **Lines**: scope, cost code, rate, measured to date, previously billed, this period qty and this period amount, with the **Gross bill value**. On a direct bill, the lines are the charges you entered.
- **Taxes and Charges**: pick a tax **Template**, or click **+ Add row** to add a tax with its account head and rate.
- **Retention, TDS &amp; Discount**: the **Retention %** (default: the work order’s), **Apply TDS (withholding)**, an **Additional discount** as % or ₹ on the Net Total (before tax) or Grand Total (after tax), and the **Expense account** where the cost posts (default: Subcontractor Charges).
- **Net payable**: the calculation, line by line.
- **Advance Payments**: click **+ Link advance** to recover an advance already paid to the subcontractor. If the subcontractor has an unlinked advance, a banner at the top says so, with a **Link advance** button.
- **Attachments**: click **+ Upload** for invoices, measurement sheets or site photos.

### How net payable is worked out


|                                  |                                                                             |
| -------------------------------- | --------------------------------------------------------------------------- |
| Gross bill value                 | Total of this period’s lines                                                |
| Taxable value                    | Gross, less any discount on net total                                       |
| + Taxes                          | From the template or rows                                                   |
| **Invoice value**                | Taxable value + taxes. This is the Purchase Invoice amount                  |
| − TDS withheld                   | If TDS is applied                                                           |
| − Retention held                 | Retention % of the gross. Held on your books and released on the final bill |
| **Net payable to subcontractor** | What is actually paid                                                       |


> *Example:* Gross ₹1,51,200, no tax, no TDS. Retention 5% = ₹7,560. Net payable = **₹1,43,640**.

### Status and actions

- **Draft**: **Edit**, **Submit** or **Delete**.
- **Submitted**, Unpaid or **Partly Paid**: **Make Payment**, **Open in Accounting** or **Cancel**.
- **Submitted**, **Paid**: **Open in Accounting** or **Cancel**.
- **Cancelled**: **Amend** or **Delete**.



**Make Payment** records a payment against the bill: the amount, date, account paid from, mode of payment and reference number. The outstanding amount goes down, and the payment status changes to **Partly Paid** or **Paid**. **Open in Accounting** opens the linked Purchase Invoice in ERPNext.

### Rules

- A bill can be edited only while it is in **Draft**.
- On a bill from a work order, quantities can’t be changed. They always come from certified Measurement Books, less what was billed before.
- Retention is held back from every bill and released on the final bill.
- Submitting a bill creates its ERPNext Purchase Invoice, and adds to **Billed** on the work order and to actual cost on the BOQ.
- To correct a submitted bill, cancel it, amend the copy and submit it again.