A **Measurement Book (MB)** records the quantity of work a subcontractor has actually completed against a work order, measured on site. Once **certified**, those quantities are what the subcontractor can be billed for.



`Open it from: Subcontract → Measurement Books`



**Before you begin**

- The **Work Order** must be submitted.

### Measurement Books list

The list shows each book’s **MB ID**, **Project**, **Work Order**, **Date**, number of **Entries**, quantity **Measured** and **Status**. You can filter by **work order**, **project**, **status** and a **measured date range**.



![](/files/imagee5d00a.webp)

### Create a Measurement Book

1. Open **Measurement Books** and click **+ New**. You can also click **+ Record measurement** on a work order.
2. Select the **Work order**. The project and subcontractor are filled in from it.
3. Set the **Date** and **Measured by**, and add remarks if needed.
4. Under **Entries**, click **+ Add entry** for each measured area. Enter what was measured, pick the **WO line**, and enter the dimensions or type the quantity.
5. Click **Create MB**. It is saved as **Draft**.
6. When the quantities have been checked, the QS certifies the book and is recorded in **Certified by**.

![](/files/image317f93.webp)

### Fields

**Header**


| Field                          | Mandatory | What it means                                                |
| ------------------------------ | --------- | ------------------------------------------------------------ |
| **Work order**                 | Yes       | The submitted work order being measured                      |
| **Project**, **Subcontractor** | Read-only | Taken from the work order                                    |
| **Date**                       | Yes       | Date of measurement. Default: today                          |
| **Status**                     | Yes       | **Draft** or **Certified**                                   |
| **Measured by**                | No        | Who took the measurements. Default: you                      |
| **Certified by**               | No        | Who checked and certified them, usually the QS               |
| **Remarks**                    | No        | For example “North and south terraces pending parapet works” |


**Entries**


| Field                        | What it means                                                           |
| ---------------------------- | ----------------------------------------------------------------------- |
| **Description**              | What was measured, for example “Terrace east, APP membrane”             |
| **WO Line**                  | The work order line this quantity counts against                        |
| **Code**                     | The cost code, taken from the WO line                                   |
| **Nos**, **L**, **B**, **D** | Number, length, breadth and depth                                       |
| **Qty**                      | Nos × L × B × D, or typed directly                                      |
| **UOM**                      | The unit, taken from the WO line                                        |
| **Deduct**                   | Tick for a deduction, such as an opening. Deduction rows are subtracted |


The **Measured Total** at the bottom is the total of all entries, less deductions.

> *Example:* Terrace east: 1 × 30 × 14 × 1 = **420 m²**. Terrace west: 1 × 21 × 10 × 1 = **210 m²**. Measured total = **630 m²**.

### The Measurement Book page

The top shows cards for the **Project**, **Work Order**, **Date**, **Measured By** (with who certified it) and **Measured Total** (with the number of entries), followed by the entries and remarks. On a certified book you can click **+ Subcontractor bill** to bill its quantities, or **Revert to Draft** to correct it.



![](/files/image80d5f4.webp)

### Rules

- A Measurement Book can be edited only while it is in **Draft**.
- Only **Certified** quantities can be billed.
- Certified quantities add to **Measured to date** on the work order’s schedule of values.
- To correct a certified book, **Revert to Draft**, fix the entries and certify it again.
- A work order with measurement books against it can’t be cancelled.