The Schedule is a Gantt chart of the project's tasks and stages. It is a view of existing records, not a separate document: tasks and stages appear as bars along their planned dates, with their dependencies and progress. 



![](/files/imageef58b7.webp)
*Schedule of a project*

---

### **Summary rows**

Tasks are grouped under summary rows. A summary row shows the earliest start and latest end of the rows under it, and their combined progress. Summary rows can be collapsed and expanded. 

---

### **Task dependencies**

A dependency links two tasks and controls their order. 


|                       |                                                  |
| --------------------- | ------------------------------------------------ |
| **Type**              | **Meaning**                                      |
| Finish-to-Start (FS)  | The second task starts after the first finishes  |
| Start-to-Start (SS)   | The second task starts when the first starts     |
| Finish-to-Finish (FF) | The second task finishes when the first finishes |




Lag adds a waiting time between the two tasks; lead lets them overlap. The system checks each dependency and refuses one that would create a loop (circular dependency). 

---

### **Rescheduling**

When a task's dates change, the tasks that depend on it can be handled in two ways: 


|           |                                                                           |
| --------- | ------------------------------------------------------------------------- |
| **Mode**  | **What happens**                                                          |
| Flag only | Affected tasks are highlighted for review; their dates do not change      |
| Cascade   | Affected tasks move automatically, keeping their dependency types and lag |




---

### **Delays**

The schedule marks tasks that are past their planned end date and not complete (overdue), and stages that are running behind their planned end date (stage slip).