title: "Bill of Quantities (BOQ)"
space: "BuildSuite Core"
url: "https://wiki.buildsuite.io/core/project-management/project-templates"
updated: "2026-11-16"
---

The BOQ lists the work for a job with quantities and rates, and gives the estimated cost. It is the base for tendering, budgeting and cost tracking.



![](/files/imagec24ed2.webp)
*BOQ list view*

### **Create a BOQ**

Click **+ New BOQ** and choose what it is for:


| Option           | Use it when                                                            |
| ---------------- | ---------------------------------------------------------------------- |
| New enquiry      | There is no project yet. Link the BOQ to a project if you win the job. |
| Existing project | You need a new version of that project’s BOQ                           |


Enter a **Title**, pick a **Customer** if you want one, and click **Create draft**. Then add groups and items, import an estimate template with **Import Template...**, or import from Excel.



![](/files/image3cb112.webp)
*BOQ  Creation*

**BOQ Structure**


| Level    | What it is                                                                       | Example                          |
| -------- | -------------------------------------------------------------------------------- | -------------------------------- |
| Group    | A section of work. The code is generated automatically (A, B, C…) if left blank. | A — Civil Works RCC              |
| Item     | A measurable piece of work, often from an assembly                               | A.06 RCC for decking slab, 38 m³ |
| Sub-item | The rate breakdown of an item, from the Rate Master                              | Cement, steel, mason, mixer      |


**11.4.3 BOQ fields**


| Field       | Type           | Mandatory | Notes                                          |
| ----------- | -------------- | --------- | ---------------------------------------------- |
| Title       | Data           | Yes       | Identifies the estimate until it has a project |
| Customer    | Link: Customer | No        | Who the job is priced for                      |
| Project     | Link: Project  | No        | Empty for an enquiry. Set when the job is won. |
| Revision    | —              | Auto      | R1, R2…                                        |
| Status      | —              | Auto      | Draft / Submitted / Approved / Replaced        |
| Tax Rate    | Percent        | No        | Default 18%                                    |
| Margin Rate | Percent        | No        | Default 10%                                    |
| Description | Text           | No        |                                                |


**11.4.4 Item fields**


| Field                | Notes                                                               |
| -------------------- | ------------------------------------------------------------------- |
| Code and Description | e.g. A.06 RCC for decking slab                                      |
| Unit, Plan Qty, Rate | Planned amount = Plan Qty × Rate                                    |
| Quantity Source      | Manual / Assembly / Template / Takeoff                              |
| Assembly             | The assembly the item came from, if any                             |
| Work Package (WP)    | The work package the cost belongs to                                |
| Task                 | Optional. Used to calculate actuals.                                |
| Cost Head            | Material / Labour / Equipment / Subcontract / Preliminaries / Other |
| Fulfilment           | Procure / Manufacture (make-or-buy)                                 |




![](/files/imagea74638.webp)
*BOQ Detailed view*



**11.4.5 Calculations**

- Item amount = Quantity × Rate
- Sub-item quantity = Coefficient × Item quantity
- Group total = Sum of its items
- BOQ total = Subtotal + Margin + Tax

Amounts are recalculated whenever a quantity or rate changes.

**11.4.6 Approval and revisions**

A draft is sent with **Submit for approval**. Each BOQ record is one revision. A project can have only one Approved revision, and approving a new one changes the previous one to Replaced. An approved BOQ is read-only. To change it, use **+ Revision**, which creates a new draft. A revision can also come from an approved scope change order (see 10.3). In that case the page shows “from SCO …”.

**11.4.7 Planned, committed and actual**

For each line and group the BOQ shows:


| Column    | Meaning                                                                                     |
| --------- | ------------------------------------------------------------------------------------------- |
| Planned   | Plan Qty × Rate                                                                             |
| Committed | Value of submitted purchase orders and subcontract work orders against the line’s cost code |
| Actual    | Cost booked so far. Refresh it with **Recalc actuals**.                                     |
| Variance  | Actual against Planned, in %                                                                |


Material ordered on the project without a cost code is not counted as committed. A banner shows its value with a link to the purchase orders.

**11.4.8 Page actions**


| Action                            | What it does                                                                                                                    |
| --------------------------------- | ------------------------------------------------------------------------------------------------------------------------------- |
| Submit for approval               | Sends a draft for approval                                                                                                      |
| Recalc actuals                    | Recalculates actuals from the linked tasks’ progress                                                                            |
| + Revision                        | Creates a new draft revision from this BOQ                                                                                      |
| Compare to R…                     | Shows the changes against the previous revision                                                                                 |
| Import Template...                | Adds the groups and items of an estimate template                                                                               |
| Import from Excel...              | Imports lines from an Excel or CSV file. The system matches the columns and asks you to approve any units it doesn’t recognise. |
| Export CSV                        | Downloads the BOQ lines                                                                                                         |
| Clone...                          | Copies the BOQ                                                                                                                  |
| Set up work packages and tasks... | Creates the project’s work packages and tasks from the BOQ                                                                      |
| Delete                            | Deletes the BOQ (drafts only)                                                                                                   |


**BOQ list:** The list shows each BOQ’s ID, what it is for (a project, or “Estimate · not yet won”), revision, status, planned, actual and variance. The cards at the top count Approved, Draft and Submitted BOQs and show the total planned value of approved BOQs.